Traffic switch on Ashley Drive duplication


Released 10/11/2017

The duplication of Ashley Drive between Erindale Drive and Johnson Drive is progressing towards completion in early 2018, reaching a key milestone today with the first stage of a traffic switch to the new section of road.

“The duplication of Ashley Drive has been underway for just over 12 months now and a number of key milestones have been reached in that time. The noise walls and works on the underground services have been completed and new infrastructure including the Statton Street and Bugden Avenue underpasses and Monks Creek Bridge has been constructed,” said Ben McHugh, Director of Capital Works and Development Support at Transport Canberra and City Services.

“Installation of streetlights and traffic lights is also nearing completion and today’s traffic switch will allow works to be undertaken on the median including completion of the stormwater and construction of traffic and pedestrian islands.

“This upgrade to Ashley Drive will significantly increase the capacity of the road and improve access for Theodore, Calwell and Lanyon residents connecting to the northern areas of the Tuggeranong Valley and Woden Valley through to the city centre.”

The first stage of the traffic switch which has been completed today, has moved southbound traffic between Isabella Drive and Johnson Drive onto the new road. This will give access to the construction team to complete their works in the median.

Milestones the project has to look forward to include:

  • Southbound traffic switch from Erindale Drive to Isabella Drive – December 2017
  • Traffic lights operational – planned for February 2018
  • Project completion – planned for March 2018 (weather permitting).

“Ashley Drive is Tuggeranong’s largest road and transport infrastructure project underway at the moment and we are working to deliver it as quickly as possible,” Mr McHugh said.

Roadside signage will alert road users to the changed traffic arrangements. A speed limit of 60km/h will remain in place until works have been finalised.

- Statement ends -