F.3 Capital Works


ICT Capital Works Projects  Estimated Completion Date  Actual Completion Date  Original Project Value  Revised Project Value  Prior Year's Expenditure  Current Year Expenditure  Total Expenditure to Date 
ICT Works in progress - CMTD        
Mobile Canberra Applications  Dec 2013 Jun 2004 70 70 30 32 62
Injury Prevention and Management Information Systems Feb 2014 Jun 2014  450 450 121 329 450
Accident and Information Management System Dec 2013 Jun 2014 3,000 3,000 1,588 1,412 3,000
Total ICT Capital Works Program   3,520 3,520 1,739 1,773 3,512

Note:  All amounts are in $'000.

Reconciliation of Funding and Expenditure

Reconciliation of Total Current Year Financing Expenditure   
Original Capital Works Financing  1,601
Revised Capital Works Financing 1,781
Add:  Reversal of Accrued Salaries 10
Add:  Reversal of Capital Works Funded through GPO  18
Add:  Savings against the Mobile Canberra Applications Project   -8
Capital Injections in 2013-14 Financial Report  1,802
Reconciliation of Total Current Year Expenditure to Capital Injections  
Total Current Year Works Expenditure   1,773
Add:  Reversal of Accrued Salaries   10
Add:  Reversal of Capital Works Funded through GPO   18
Capital Injections in 2013-14 Financial Reports  1,802